Chris Hefley
posted this on July 11, 2011 01:57 pm
Using these trend lines, teams can get an good understanding of how quickly they are processing work and whether the current velocity is sufficient to process the work within a system over a given time frame. The information presented also informs teams of what rate is required to complete the remaining work from the current date.
To include the Burn-up trajectory trends in the CFD diagram, you will need to check the "Calculate Burn-up Trajectory" located in the Additional Criteria section underneath the chart area. After checking this option, you will be presented with some additional criteria.
Criteria
All the standard criteria for the CFD can be applied with one exception, you cannot exclude a lane that is follows the selected Burn-up Lane.
After running the CFD with the Burn-up Trajectory, you will see that there are some additional graph elements included. You will also see that the end date on the graph extends to the selected end date for the Burn-up trajectory. Lets take a look at an example of the output.
In the example above, we can see that our overall WIP within the systems is increasing by about 0.43 Cards a day. In order to process all the WIP from the specified start date to the end date, we would need to average about 0.55 Cards a day. As you can see our throughout has actually been about 0.21 Cards a day. Therefore we are not on track to process all of the WIP before the end date. In order to catch up and finish all the work, we will now need to complete 0.87 Cards a day for the remainder of the time frame.